WE’RE FOLLOWING MAHARISHI BHAGWAN VALMIKI JI’S PATH TO BUILD PUNJAB ROOTED IN EQUALITY, DIGNITY & JUSTICE: CM BHAGWANT SINGH MANN* ENSURING BENEFITS OF GOVT SCHEMES REACH THE POOREST IN SOCIETY IS THE GOVERNMENT’S PRIORITY: CM NAYAB SINGH SAINI FROM DY. SECY IN HPSC SINCE FEB, 2022 TO ELITE POST OF CHAIRMAN, HPSC TILL SEP, 2032 FORMER CONGRESS MLA RAMINDER SINGH AWLA JOINS SAD ABOHAR NATIVE GARRY THIND WINS IN THE PROVINCIAL ELECTION IN CANADA GUEST TEACHERS BEGIN NYAY YATRA FROM KURUKSHETRA TO CHANDIGARH DEMAND REGULARISATION OF SERVICES DIGNITARIES PAY TRIBUTE TO SCRIBES FAMILY’S DEPARTED CHIEF SAMPLA AND ANGURAL QUESTION THE GOVERNMENT'S HANDLING OF THE AJAY'S MURDER CASE ELECTION COMMISSION'S 16 LAKH APPEALS AGAINST JUDGE-CLEARED BENGAL VOTERS QUESTIONED: KBS SIDHU SEEKS PUBLIC ANSWERS, INVOKES RT DAV COLLEGE OF EDUCATION SCRIPTS HISTORY WITH 12TH CONSECUTIVE ZONAL YOUTH FESTIVAL TROPHY
Himachal Trending

SJVN BAGS ANOTHER 200 MW SOLAR PROJECT, PORTFOLIO CROSSES 47000 MW

Read in:English

(MOREPIC1)   Face2News/Shimla

Mr Nand Lal Sharma, Chairman & Managing Director, SJVN  informed that SJVN has obtained 200 MW Grid Connected Solar Power Project in Khavda Solar Park through e-Reverse auction conducted by Gujarat Urja Vikas Nigam Limited (GUVNL).

Nand Lal Sharma stated that SJVN bagged the full quoted capacity of 200 MW @ Rs 2.88 per unit on Build Own and Operate basis under Open Competitive Tariff bidding by GUVNL. This solar project shall be developed by SJVN in Khavda Solar Park, Gujarat. The tentative cost for development of this project shall be approximately Rs 1200 Crores.

(SUBHEAD)Further apprising about the project, Nand Lal Sharma said that the project is expected to generate 505 million units in 1st year of commissioning and cumulative energy generation over a period of 25 years would be around 11756 million units. Commissioning of the project is expected to reduce 5,76,067 tonnes of carbon emission.

“Our vision is aligned with the government’s vision for a carbon neutral economy. With the allotment of this project, our solar & wind portfolio stand at 17620 MW out of which 179.5 MW is under operation and rest is under various stages of implementation,” said Sharma.

SJVN is on a rapid expansion and capacity addition journey and with allocation of this solar project, the project portfolio of the company is now 47079 MW. The company is marching forward with vigour to achieve its Shared Vision of 5000 MW by 2023-24, 25000 MW by 2030 & 50000 MW installed capacity by 2040.